Turkish demo site: A detailed plan for delivering a successful retrofit

Since the beginning of the year 2015, the technical specifications of both the active and passive works have been drawn up and in February a first meeting was held with the hospital procurement team.
For the solar and ORC systems to be installed in the Turkish Demo (a Public Hospital in the city of Aydin), manufacturing has already started and is set to continue until the last quarter of 2015. Tendering for the purchase of some of the technologies, such as the adsorption chiller, and the ventilated façade installation works, are underway and should be completed by the end of July.