-
-
August 2015 – Behind technical room – Area for «biomass storage» and «dry-cooler»
-
September 2015: Cleaning and preparation works - Area for «biomass storage» and «dry-cooler»
-
October 2015: Space for silo to store the pellets and biomass boiler
-
November 2015: Installation of pipings between the
existing and the new technical room
-
December 2015 – The urban permit for the
planned work awarded
-
January 2016 - Demo site facilities
-
February 2016 - Dismantling Curtain Wall A: Main Entrance
-
February 2016 - Dismantling: Inside works
-
March 2016 – Retrofitting the façade
-
March 2016 – Retrofitting inside
-
March 2016 - Preparing the façade…
-
April 2016 - Removing windows and frames
-
April 2016 - Main façade
-
April 2016 - Replacement of windows: Rear Façade Block N° 6
-
April 2016 - Replacement of windows:
Façade Block N° 6 in patio
-
May 2016 - Building of ceilings (Fire Resistant)
-
May 2016 - Main facade
-
May 2016 - Replacement of windows:
Façade Block N° 6 in patio
-
June 2016 - insulation being applied
-
June 2016 - Further fire-resistant ceilings
-
July 2016 - Completion of façade windows
-
September 2016 - Ceiling insulation continues
-
September 2016 - Roughcasting on the back of façade in block 6
-
September 2016 - Roof insulation for block 1
-
September 2016 - Insulation and waterproofing for block 1
-
September 2016 - Greencom ventilation units
-
October 2016 - Greencoms Ventilation units
-
October 2016 - Sensors in Purinovas panels
-
November 2016 – BRICKER team in front of old and
new façades of the demo site
-
November 2016 – BRICKER team visiting the old boiler room
-
November 2016 - Greencom Ventilation gates in the windowsframes
-
November 2016 - Completion casings in lecture hall 428
-
December 2016 - Assembly of the cyclone of the biomass boiler
-
December 2016 - Smoke extractor of the boiler
-
December 2016 - Handling of silos for pellets storage
-
February 2017 - Concrete slab supporting the expander vessel for thermal oil
-
February 2017 - Delivery of 1000L tank for thermal oil
-
February 2017 - Insulation and plastering for block 1
-
March 2017 - Expansion vessels for thermal oil
-
March 2017 - Fibre cement pannels for block 6
-
March 2017 - Final look of the faade
-
March 2017 - Piping for moving pellets from truck to silos
-
March 2017 - Transport system for pellets
-
April 2017 - wall insulation in courtyard
-
May 2017 - New heat exchanger between ORC unit and cooling tower
-
June 2017 - connection for 500kW dry cooler
-
June 2017 - pressure sensors - biomass boiler
-
July 2017 - dilatation joint connection between technical rooms