Intervention progress at the Belgian Demo Site

The retrofitting works at the Belgian demo site started in September 2015. The image gallery below shows the works as they progressed. Click here to access the monthly technical progress reports.

  • August 2015 – Behind technical room – Area for «biomass storage» and «dry-cooler»
  • September 2015: Cleaning and preparation works - Area for «biomass storage» and «dry-cooler»
  • October 2015: Space for silo to store the pellets and biomass boiler
  • November 2015: Installation of pipings between the
    existing and the new technical room
  • December 2015 – The urban permit for the
    planned work awarded
  • January 2016 - Demo site facilities
  • February 2016 - Dismantling Curtain Wall A: Main Entrance
  • February 2016 - Dismantling: Inside works
  • March 2016 – Retrofitting the façade
  • March 2016 – Retrofitting inside
  • March 2016 - Preparing the façade…
  • April 2016 - Removing windows and frames
  • April 2016 - Main façade
  • April 2016 - Replacement of windows: Rear Façade Block N° 6
  • April 2016 - Replacement of windows:
    Façade Block N° 6 in patio
  • May 2016 - Building of ceilings (Fire Resistant)
  • May 2016 - Main facade
  • May 2016 - Replacement of windows:
    Façade Block N° 6 in patio
  • June 2016 - insulation being applied
  • June 2016 - Further fire-resistant ceilings
  • July 2016 - Completion of façade windows
  • September 2016 - Ceiling insulation continues
  • September 2016 - Roughcasting on the back of façade in block 6
  • September 2016 - Roof insulation for block 1
  • September 2016 - Insulation and waterproofing for block 1
  • September 2016 - Greencom ventilation units
  • October 2016 - Greencoms Ventilation units
  • October 2016 - Sensors in Purinovas panels
  • November 2016 – BRICKER team in front of old and
    new façades of the demo site
  • November 2016 – BRICKER team visiting the old boiler room
  • November 2016 - Greencom Ventilation gates in the windowsframes
  • November 2016 - Completion casings in lecture hall 428
  • December 2016 - Assembly of the cyclone of the biomass boiler
  • December 2016 - Smoke extractor of the boiler
  • December 2016 - Handling of silos for pellets storage
  • February 2017 - Concrete slab supporting the expander vessel for thermal oil
  • February 2017 - Delivery of 1000L tank for thermal oil
  • February 2017 - Insulation and plastering for block 1
  • March 2017 - Expansion vessels for thermal oil
  • March 2017 - Fibre cement pannels for block 6
  • March 2017 - Final look of the faade
  • March 2017 - Piping for moving pellets from truck to silos
  • March 2017 - Transport system for pellets
  • April 2017 - wall insulation in courtyard
  • May 2017 - New heat exchanger between ORC unit and cooling tower
  • June 2017 - connection for 500kW dry cooler
  • June 2017 - pressure sensors - biomass boiler
  • July 2017 - dilatation joint connection between technical rooms